Research project
Ghana's unfinished public projects
Which of Ghana's public projects stand unfinished, stalled or abandoned: what did each cost, what was paid, what stands today, and does it operate?
- Status
- Collecting
- Last update
- 2026-11-14
Findings so far
No findings yet: the register has published no release.
Method
A sourced register. Each project is one record; every claim about it (a contract sum, a payment, its physical state, whether it operates) is a separate dated observation with its source, the page it comes from and an evidence tag: FACT, FUNDED, ANNOUNCED or REPEATED. Physical completion and operation are separate claims, and claims that disagree sit side by side. Money keeps the currency the source gives. The records are validated before each dated release, and a release is never edited: a correction is a new release.
Sources
- Reports of the Auditor-General (Ghana Audit Service)
Terms: not stated · Refresh: annual
- MMDA composite budgets, Public Investment Plan tables (Ministry of Finance)
Terms: not stated · Refresh: annual
- MMDA Annual Progress Reports (National Development Planning Commission)
Terms: not stated · Refresh: annual
- Replication data for Williams (2017), local government projects 2010–2013 (Harvard Dataverse)
Terms: CC0 1.0 · Refresh: none
- World Bank Projects API, Ghana
Terms: not stated · Refresh: irregular
Log
- Literature review and source map: what research has measured, and the public data series that list projects with their cost, payments and state.
- Record schema settled: projects, dated observations and sources, with a validator that refuses a claim without a source, a date or an evidence tag.
Data
Release 2026-11-14 · as of 2026-11-14 · schema 1 · CC BY 4.0
observations.csvobservations.jsonprojects.csvprojects.jsonsources.csvsources.jsonmanifest.json
5 of 5
| Project | Sector | Region | District | Physical state | Operating | Contract sum | Funders |
|---|---|---|---|---|---|---|---|
| Agenda 111 | health | multiple | in progress (2026-07-09) | not operating (2026-07-09) | Government of Ghana | ||
| Kpone Affordable Housing Project | housing | Greater Accra | Kpone Katamanso Municipality | in progress (2026-04-15) | partly operating (2026-04-15) | ||
| Saglemi Affordable Housing Project | housing | Greater Accra | Ningo Prampram Municipality | in progress (2026-08-20) | not operating (2026-08-20) | USD 200,000,000 (2013-01-04) | Credit Suisse International |
| Tema-Mpakadan Railway Line | rail | multiple | in progress (2026-07-06) | unknown (2026-07-06) | USD 447,000,000 (2025-05-20) | Export-Import Bank of India, European Union (signalling grant) | |
| Weija Children's Hospital | health | Greater Accra | Weija-Gbawe Municipality | in progress (2026-10-03) | partly operating (2026-10-03) | USD 10,150,000 (2026-05-25) | World Bank |
Source: Ghana's unfinished public projects, release 2026-11-14 (as of 2026-11-14), CC BY 4.0.
- health2
- housing2
- rail1
Table
| Sector | Projects |
|---|---|
| health | 2 |
| housing | 2 |
| rail | 1 |
Source: Ghana's unfinished public projects, release 2026-11-14 (as of 2026-11-14), CC BY 4.0.
- Credit Suisse International1
- European Union (signalling grant)1
- Export-Import Bank of India1
- Government of Ghana1
- not stated1
- World Bank1
Table
| Funder | Projects |
|---|---|
| Credit Suisse International | 1 |
| European Union (signalling grant) | 1 |
| Export-Import Bank of India | 1 |
| Government of Ghana | 1 |
| not stated | 1 |
| World Bank | 1 |
Source: Ghana's unfinished public projects, release 2026-11-14 (as of 2026-11-14), CC BY 4.0.
- Greater Accra3
- multiple2
Table
| Region | Projects |
|---|---|
| Greater Accra | 3 |
| multiple | 2 |
Source: Ghana's unfinished public projects, release 2026-11-14 (as of 2026-11-14), CC BY 4.0.
FACTFUNDEDANNOUNCEDREPEATED
Agenda 111 · 9 claims
2026-07-092026-07-09
| As of | Claim | Tag | Source |
|---|---|---|---|
| 2026-07-09 | allegation: Some Agenda 111 hospitals were commissioned with temporary arrangements: generators were brought for the ceremony and removed afterwards, and the premises were locked. (stated by Health Minister (statement to Parliament's Assurance Committee))in some cases, generators were carried to the site for the commissioning, and after the commissioning, it was taken back, and the place was locked. | ANNOUNCED | MyJoyOnline, article paragraph 16 |
| 2026-07-09 | amount outstanding: GHS 1,000,000,000 (stated by Health Minister (statement to Parliament's Assurance Committee))the government inherited more than GH¢1 billion in outstanding Interim Payment Certificates (IPCs) owed to contractors | FACT | MyJoyOnline, article paragraph 2 |
| 2026-07-09 | amount paid: GHS 4,800,000,000 (stated by Health Minister (statement to Parliament's Assurance Committee))despite the previous administration spending about GH¢4.8 billion on the initiative | FACT | MyJoyOnline, article paragraph 1 |
| 2026-07-09 | announcement: 35 Agenda 111 projects identified for continuation; contractors directed to return to site; no completion dates given because some contracts may be terminated and repackaged. (stated by Health Minister (statement to Parliament's Assurance Committee))the government has identified 35 Agenda 111 projects for continuation, with contractors directed to return to their respective sites. | ANNOUNCED | MyJoyOnline, article paragraph 3 |
| 2026-07-09 | announcement: The 2026 Budget provides for work to start on 10 of the 35 identified projects. (stated by Health Minister (statement to Parliament's Assurance Committee))if you check the 2026 Budget, we said we were going to start 10 in 2026. | FUNDED | MyJoyOnline, article paragraph 7 |
| 2026-07-09 | announcement: Church or CHAG partners may complete, equip and operate Agenda 111 facilities under agreements with the Ministry. (stated by Health Minister (statement to Parliament's Assurance Committee))if any church is interested in any of the Agenda 111 facilities, we will enter into an agreement with the church or CHAG and they will finish, equip and then operationalise it | ANNOUNCED | Citi Newsroom, article paragraph 8 |
| 2026-07-09 | cost to complete: GHS 20,000,000,000 (stated by Health Minister (statement to Parliament's Assurance Committee))We need a little above 20 billion Ghana cedis. | ANNOUNCED | Citi Newsroom, article paragraph 4 |
| 2026-07-09 | operational state: not operating (stated by Health Minister (statement to Parliament's Assurance Committee))the Minister answered, "Zero." | FACT | MyJoyOnline, article paragraph 12 |
| 2026-07-09 | physical state: in progress (stated by Health Minister (statement to Parliament's Assurance Committee))About three were commissioned, while they were not completed. | FACT | MyJoyOnline, article paragraph 14 |
Kpone Affordable Housing Project · 11 claims
2024-11-262026-04-15
| As of | Claim | Tag | Source |
|---|---|---|---|
| 2024-11-26 | allegation: The project was abandoned between 2009 and 2016 and was revived by the new board and management of the Tema Development Corporation. (stated by Vice-President (speech at the inauguration and sod-cutting))was abandoned between 2009 and 2016 | ANNOUNCED | Graphic Online, article paragraph 4 |
| 2024-11-26 | capacity: 1072 units (stated by Graphic Online (reporter))inaugurated a 1,072 housing units part of the Kpone (Community 26) affordable housing facility | FACT | Graphic Online, article paragraph 3 |
| 2024-11-26 | capacity: 832 units (stated by Vice-President (speech at the inauguration and sod-cutting))cut the sod for the construction of 832 additional housing units at Kpone | ANNOUNCED | Graphic Online, article paragraph 1 |
| 2024-11-26 | commissioning date: 2024-11 (stated by Graphic Online (reporter))inaugurated a 1,072 housing units part of the Kpone (Community 26) affordable housing facility | FACT | Graphic Online, article paragraph 3 |
| 2024-11-26 | start date: 2006 (stated by Vice-President (speech at the inauguration and sod-cutting))started in 2006 | ANNOUNCED | Graphic Online, article paragraph 4 |
| 2026-04-15 | announcement: Contracts under the project could be terminated over poor performance; one contractor responsible for 10 blocks is significantly behind schedule. (stated by Managing Director, TDC Ghana Ltd)warned contractors under the Kpone Affordable Housing Project that contracts could be terminated over poor performance | ANNOUNCED | Graphic Online, article paragraph 17 |
| 2026-04-15 | capacity: 800 units (stated by Minister for Works, Housing and Water Resources)the significant progress made on the 800 two-bedroom housing units under Phase Four of the Kpone Affordable Housing Project | ANNOUNCED | Graphic Online, article paragraph 4 |
| 2026-04-15 | completion date planned: 2026-09 (stated by Minister for Works, Housing and Water Resources)which is expected to be completed by September this year | ANNOUNCED | Graphic Online, article paragraph 4 |
| 2026-04-15 | operational state: partly operating (stated by Minister for Works, Housing and Water Resources)Already, Phases One to Three of the project have delivered 1,000 housing units. | FACT | Graphic Online, article paragraph 8 |
| 2026-04-15 | physical progress: 90% (stated by Information Services Department, reporting the Minister's inspection)Work on both phases, which commenced in 2025, is now 90% complete. | FACT | Information Services Department, article paragraph 2 |
| 2026-04-15 | physical state: in progress (stated by Graphic Online (reporter, on the Minister's inspection))Construction, which began in 2025, has reached advanced stages, with several buildings currently at roofing, plastering and painting levels. | FACT | Graphic Online, article paragraph 5 |
Saglemi Affordable Housing Project · 20 claims
2012-082026-08-24
| As of | Claim | Tag | Source |
|---|---|---|---|
| 2012-08 | capacity: 5000 units (stated by Attorney-General (court filing, as reported by MyJoyOnline))granted executive approval to the Ministry of Water Resources, Works and Housing (MWRWH) for the construction of 5000 affordable housing units (the Saglemi Affordable Housing Project) | FACT | MyJoyOnline, article paragraph 8 |
| 2013-01-04 | award date: 2013-01-04 (stated by Attorney-General (court filing, as reported by MyJoyOnline))signed an Engineering, Procurement and Construction (EPC) Agreement with Construtora OAS Ghana Ltd | FACT | MyJoyOnline, article paragraph 12 |
| 2013-01-04 | contract sum: USD 200,000,000 (stated by Attorney-General (court filing, as reported by MyJoyOnline))at a contract price of US$ 200million, including consultancy services | FACT | MyJoyOnline, article paragraph 13 |
| 2013-01-04 | loan amount: USD 200,000,000 (stated by Attorney-General (court filing, as reported by MyJoyOnline))On 4th January 2013, a Facility Agreement was signed between the Ministry of Finance, as the borrower, and Credit Suisse, as the creditor, for a facility of $200million for the construction of 5000 housing units. | FACT | MyJoyOnline, article paragraph 11 |
| 2016-12-21 | capacity: 1412 units (stated by Attorney-General (court filing, as reported by MyJoyOnline))further reduction in the scope of works to 1,412 housing units | FACT | MyJoyOnline, article paragraph 32 |
| 2016-12-21 | completion date planned: 2017-07-31 (stated by Attorney-General (court filing, as reported by MyJoyOnline))extended the completion period of the contract to 31st July 2017 without any basis | ANNOUNCED | MyJoyOnline, article paragraph 32 |
| 2016-12-21 | revised contract sum: USD 181,018,000 (stated by Attorney-General (court filing, as reported by MyJoyOnline))revised contract price of US$ l81,018,000.00 and extended the completion period of the contract to 31st July 2017 | FACT | MyJoyOnline, article paragraph 32 |
| 2021-08-01 | allegation: The contractor was paid US$179.9m although the cost of works executed on site, including consultancy services, was about US$64.98m; only 668 housing units were completed, none habitable or sold, and the facility remains unpaid. (stated by Attorney-General (court filing))investigations revealed that the cost of works executed on the site, including consultancy services, is about $64,982,900.77. | ANNOUNCED | MyJoyOnline, article paragraph 37 |
| 2021-08 | amount paid: USD 179,904,757.78 (stated by Attorney-General (court filing, as reported by MyJoyOnline))with the contractor having been paid $179,904, 757.78 | ANNOUNCED | MyJoyOnline, article paragraph 37 |
| 2021-08 | amount paid: USD 196,428,891.66 (stated by Attorney-General (court filing, as reported by MyJoyOnline))Even though a total amount of $196,428,891.66 has been spent on the Saglemi Affordable Housing Project | ANNOUNCED | MyJoyOnline, article paragraph 37 |
| 2021-08-01 | capacity: 668 units (stated by Attorney-General (court filing, as reported by MyJoyOnline))Investigations further revealed that only 668 housing units were completed by the contractor. | ANNOUNCED | MyJoyOnline, article paragraph 38 |
| 2021-08-01 | operational state: not operating (stated by Attorney-General (court filing, as reported by MyJoyOnline))These houses are, however, not habitable and none under the project has been sold and the Facility remains unpaid | ANNOUNCED | MyJoyOnline, article paragraph 39 |
| 2025 | physical state: stalled (stated by President (Presidency statement and site tour, 20 August 2026))before it stalled following a change of government and subsequent legal and investigative issues | ANNOUNCED | MyJoyOnline, article paragraph 5 |
| 2025-02-07 | decision: The Attorney-General withdrew all charges in the Saglemi case against the five accused by a nolle prosequi notice filed at the High Court (Financial Division 1) on 7 February 2025. (stated by Attorney-General (nolle prosequi notice))The notice, signed by the Attorney-General, officially marks the end of the state's case against the accused individuals. | FACT | Citi Newsroom, article paragraph 3 |
| 2026-08-20 | allegation: The stalled site was vandalised: cables, wash basins, baths, fittings and bulbs were stolen, and underground telecommunications cables removed. (stated by President (Presidency statement and site tour, 20 August 2026))Looters came in and stole everything, the cables, the wash basins, the baths, all the fittings, electrical bulbs | ANNOUNCED | MyJoyOnline, article paragraph 8 |
| 2026-08-20 | completion date planned: 2027-03 (stated by President (Presidency statement and site tour, 20 August 2026))the first 700 housing units at the Saglemi Affordable Housing Project are expected to be completed and commissioned by March 2027 | ANNOUNCED | MyJoyOnline, article paragraph 1 |
| 2026-08-20 | completion date planned: 2027-12 (stated by President (Presidency statement and site tour, 20 August 2026))1,500 housing units to be completed by the end of 2027 | ANNOUNCED | MyJoyOnline, article paragraph 2 |
| 2026-08-20 | operational state: not operating (stated by MyJoyOnline (reporter))prospective homeowners to prepare to register for the houses once the official registration portal is opened. | ANNOUNCED | MyJoyOnline, article paragraph 4 |
| 2026-08-20 | physical state: in progress (stated by MyJoyOnline (reporter, on the President's tour))where construction work is ongoing to complete the residential community | ANNOUNCED | MyJoyOnline, article paragraph 3 |
| 2026-08-24 | announcement: Work is to begin immediately on a further 3,500 units, to bring the estate to the 5,000 units originally planned. (stated by President (working tour of Saglemi))while work would begin immediately on the additional 3,500 units to bring the estate to the 5,000 units originally envisaged | ANNOUNCED | Ghanaian Times, article paragraph 3 |
Tema-Mpakadan Railway Line · 11 claims
2025-05-202026-07-06
| As of | Claim | Tag | Source |
|---|---|---|---|
| 2025-05-20 | announcement: About 75 per cent of the vandalism and theft damage has been repaired; commercial operations were held back by theft and vandalism and by the absence of private operators. (stated by Acting Chief Executive Officer, Ghana Railway Development Authority)about 75 per cent of the damage has so far been repaired | ANNOUNCED | Graphic Online, article paragraph 8 |
| 2025-05-20 | announcement: Full commercial operations could begin by 20 June 2026. (stated by Acting Chief Executive Officer, Ghana Railway Development Authority)full commercial operations could begin by June 20, 2026. | ANNOUNCED | Graphic Online, article paragraph 13 |
| 2025-05-20 | capacity: 97.7 km (stated by Graphic Online (reporter))Six months after the official opening of the 97.7-kilometre Tema-Mpakadan railway operations on Friday, November 22, 2024, the much-publicised service remains inactive | FACT | Graphic Online, article paragraph 1 |
| 2025-05-20 | commissioning date: 2024-11-22 (stated by Graphic Online (reporter))Six months after the official opening of the 97.7-kilometre Tema-Mpakadan railway operations on Friday, November 22, 2024, the much-publicised service remains inactive | FACT | Graphic Online, article paragraph 1 |
| 2025-05-20 | operational state: not operating (stated by Graphic Online (reporter))Six months after the official opening of the 97.7-kilometre Tema-Mpakadan railway operations on Friday, November 22, 2024, the much-publicised service remains inactive | ANNOUNCED | Graphic Online, article paragraph 1 |
| 2025-05-20 | physical state: completed (stated by Graphic Online (reporter))Constructed at a cost of US$447 million through a credit facility from the India Export-Import Bank | ANNOUNCED | Graphic Online, article paragraph 3 |
| 2025-05-20 | total cost: USD 447,000,000 (stated by Graphic Online (reporter, no document cited))Constructed at a cost of US$447 million through a credit facility from the India Export-Import Bank | ANNOUNCED | Graphic Online, article paragraph 3 |
| 2025-10-01 | operational state: partly operating (stated by Graphic Online (reporter))The Ghana Railways Development Authority (GRDA) on Wednesday, October 1, 2025, reactivated commercial operations on the Tema-Mpakadan railway line. | FACT | Graphic Online, article paragraph 1 |
| 2026-07-06 | grant amount: USD 21,000,000 (stated by Chief Executive Officer, Ghana Railway Development Authority)we have been awarded 21 million US dollars by the EU Commission as a grant to fix the signalling system with ETCS Level 1 | FUNDED | Citi Newsroom, article paragraph 8 |
| 2026-07-06 | operational state: unknown (stated by Citi Newsroom (reporter))following concerns about its readiness for full commercial operation | ANNOUNCED | Citi Newsroom, article paragraph 1 |
| 2026-07-06 | physical state: in progress (stated by Ghana Railway Development Authority (press briefing, as reported by Citi Newsroom))a forensic audit conducted under the current administration revealed that several essential systems on the line were either incomplete or not functional at the time of its commissioning | ANNOUNCED | Citi Newsroom, article paragraph 2 |
Weija Children's Hospital · 26 claims
2025-12-122026-10-03
| As of | Claim | Tag | Source |
|---|---|---|---|
| 2025-12-12 | allegation: The World Bank cancelled the construction contract, stopping work; the cancellation is said to rest on price inconsistencies, no Public Procurement Authority approval and no value-for-money audit. (stated by MyJoyOnline (reporter, relaying concerned residents and activists))The cancellation of the project is said to be due to price inconsistencies, lack of approval from the Public Procurement Authority (PPA), and the lack of a value for money audit, among others. | ANNOUNCED | MyJoyOnline, article paragraph 3 |
| 2025-12-12 | announcement: No notice of termination or cancellation has been received; the contract is with the Ministry of Health, not the World Bank; the only outstanding issue is payments due from the Ministry; the contractor gave no interview to any media house. (stated by Awerco Construction Limited (press release dated 12 December 2025, signed by its Managing Director))there has been no notice whatsoever of contract termination or cancellation | ANNOUNCED | MyJoyOnline, article paragraph 5 |
| 2025-12-12 | physical progress: 65% (stated by MyJoyOnline, attributing the figure to the contractor on site (Awerco Construction Limited))The new 120-bed facility valued at $14 million is already 65% complete, according to the contractor on the site | ANNOUNCED | MyJoyOnline, article paragraph 5 |
| 2025-12-12 | physical state: stalled (stated by MyJoyOnline (reporter, relaying activists and residents))has stalled due to an alleged unilateral abrogation of the contract for its construction by the funding agency | ANNOUNCED | MyJoyOnline, article paragraph 1 |
| 2025-12-12 | physical state: in progress (stated by Awerco Construction Limited (press release dated 12 December 2025))the Weija Paediatric Hospital Project is practically completed in line with the contract scope and is currently undergoing snagging works in collaboration with the Ministry of Health. | ANNOUNCED | MyJoyOnline, article paragraph 3 |
| 2025-12-12 | total cost: USD 14,000,000 (stated by MyJoyOnline (reporter, no document cited))The new 120-bed facility valued at $14 million is already 65% complete, according to the contractor on the site | ANNOUNCED | MyJoyOnline, article paragraph 5 |
| 2025-12-16 | announcement: The World Bank project (P173788) closed on 16 December 2025 after a six-month extension. (stated by World Bank (statement of 25 May 2026))the project officially closed on December 16, 2025, after a six-month extension | FACT | MyJoyOnline, article paragraph 4 |
| 2025-12-16 | physical state: in progress (stated by World Bank (statement of 25 May 2026))several components of the project remained unfinished, including the installation of some medical equipment | FACT | MyJoyOnline, article paragraph 7 |
| 2026-05-06 | allegation: In 2024 the World Bank raised concerns about misprocurement, including medical equipment priced up to about 11 times the actual price, and declined to settle all outstanding payments. (stated by Ministry of Health spokesperson)in 2024, the World Bank raised concerns about misprocurement, which included inflated costs of medical equipment—up to about 11 times the actual price. | ANNOUNCED | Adomonline, article paragraph 5 |
| 2026-05-06 | allegation: The contractor halted the Ministry's preparations to commission the hospital, insisting that all outstanding issues be resolved before it granted access. (stated by Ministry of Health spokesperson)the contractor subsequently halted this process, insisting that all outstanding issues be fully resolved before granting access to the hospital. | ANNOUNCED | Adomonline, article paragraph 9 |
| 2026-05-06 | completion date planned: 2025-12 (stated by Ministry of Health spokesperson)The hospital is a World Bank-funded project, which commenced in 2023 and was expected to be completed in December 2025 | ANNOUNCED | Adomonline, article paragraph 3 |
| 2026-05-06 | operational state: not operating (stated by Ministry of Health spokesperson)Despite efforts to make the facility operational, the process was halted. | ANNOUNCED | Adomonline, article paragraph 8 |
| 2026-05-06 | start date: 2023 (stated by Ministry of Health spokesperson)The hospital is a World Bank-funded project, which commenced in 2023 and was expected to be completed in December 2025 | FACT | Adomonline, article paragraph 3 |
| 2026-05-25 | capacity: 120 beds (stated by World Bank (statement of 25 May 2026))the 120-bed specialised paediatric hospital at Weija was built and equipped under the World Bank-funded COVID-19 Emergency Preparedness and Response Project at a total cost of US$10.15 million | FACT | MyJoyOnline, article paragraph 2 |
| 2026-05-25 | operational state: not operating (stated by World Bank (statement of 25 May 2026))To fully operationalise the hospital, the Government will need to complete these necessary actions and assign staff to the facility | FACT | MyJoyOnline, article paragraph 12 |
| 2026-05-25 | total cost: USD 10,150,000 (stated by World Bank (statement of 25 May 2026))the 120-bed specialised paediatric hospital at Weija was built and equipped under the World Bank-funded COVID-19 Emergency Preparedness and Response Project at a total cost of US$10.15 million | FACT | MyJoyOnline, article paragraph 2 |
| 2026-07-08 | allegation: In the course of construction the World Bank raised issues of misprocurement. (stated by Health Minister (statement to Parliament, 8 July 2026))the World Bank raised issues of what we call misprocurement | ANNOUNCED | MyJoyOnline, article paragraph 5 |
| 2026-07-08 | announcement: The Ministry will commission the hospital within 24 hours of handover, with the full complement of staff on standby. (stated by Health Minister (statement to Parliament, 8 July 2026))if the project is handed over this morning, within the next 24 hours, we don't even need any fanfare. We will commission the project because we have the full complement of staff for that particular facility | ANNOUNCED | MyJoyOnline, article paragraph 11 |
| 2026-07-08 | operational state: not operating (stated by Health Minister (statement to Parliament, 8 July 2026))the hospital cannot begin operations because some critical components, including the installation of medical equipment, are yet to be completed | ANNOUNCED | MyJoyOnline, article paragraph 3 |
| 2026-07-08 | physical state: in progress (stated by Health Minister (statement to Parliament, 8 July 2026))the contractor’s inability to complete outstanding works and officially hand over the facility to the Ministry | ANNOUNCED | MyJoyOnline, article paragraph 1 |
| 2026-07-16 | physical state: completed (stated by Economic and Organised Crime Office (statement dated 16 July 2026, as reported by Citi Newsroom))The parties agreed that the completed facility should be handed over and made operational without further delay, in the interest of the public. | ANNOUNCED | Citi Newsroom, article paragraph 3 |
| 2026-08-07 | announcement: The contractor handed the hospital over to the Ministry of Health on 7 August 2026, monitored by EOCO. EOCO's investigations into alleged procurement breaches and financial impropriety on the project remain ongoing. (stated by Economic and Organised Crime Office (statement of 11 August 2026, as reported by MyJoyOnline))The handover ceremony, monitored by the Economic and Organised Crime Office (EOCO), took place on August 7, 2026, at the Conference Room of the Weija Paediatric Hospital. | FACT | MyJoyOnline, article paragraph 2 |
| 2026-08-11 | capacity: 130 beds (stated by Economic and Organised Crime Office (as reported by MyJoyOnline))has handed over the 130-bed facility to the Ministry of Health | ANNOUNCED | MyJoyOnline, article paragraph 1 |
| 2026-10-03 | announcement: Ten additional doctors and 30 nurses and midwives are to be deployed to the hospital with immediate effect. (stated by Health Minister (announcement after an inspection))I have directed that with immediate effect, they should bring an additional 10 medical doctors and 30 nurses and midwives to beef up the health workforce. | ANNOUNCED | MyJoyOnline, article paragraph 8 |
| 2026-10-03 | operational state: partly operating (stated by Health Minister (announcement after an inspection))The Weija Children’s Specialist Hospital is now operational, with the 120-bed facility providing outpatient and emergency services | FACT | MyJoyOnline, article paragraph 1 |
| 2026-10-03 | physical state: in progress (stated by Health Minister (announcement after an inspection))almost all the equipment required for the facility had been installed | FACT | MyJoyOnline, article paragraph 6 |
Source: Ghana's unfinished public projects, release 2026-11-14 (as of 2026-11-14), CC BY 4.0.
Quote text is the work of its source, reproduced with its citation for research and comment. It is left out for every source whose quote_policy is omit.
FewerMore (most: 1)
Not on the map: no district given (2).
Table
| District | Projects |
|---|---|
| Kpone Katamanso | 1 |
| Ningo/prampram | 1 |
| Weija Gbawe Municipal | 1 |
Source: Ghana's unfinished public projects, release 2026-11-14 (as of 2026-11-14), CC BY 4.0.
Boundaries: geoBoundaries (William & Mary geoLab), from USAID Ghana HPNO and the Ghana Statistical Service, CC BY 4.0; the release's districts are at the 2019 vintage.