    "id": "agenda-111#1",
    "project": "agenda-111",
    "field": "operational_state",
    "value": "not_operating",
    "unit": null,
    "as_of": "2026-07-09",
    "source": "joy-2026-07-09-agenda-111",
    "locator": "article paragraph 12",
    "quote": "the Minister answered, \"Zero.\"",
    "stated_by": "Health Minister (statement to Parliament's Assurance Committee)",
    "tag": "FACT",
    "basis": "per_source",
    "source_term": "Zero",
    "note": "Answer to the committee's question on how many Agenda 111 hospitals were functional. The Minister's own count; the Ministry's site-by-site assessment is not published."
  },
  {
    "id": "agenda-111#2",
    "project": "agenda-111",
    "field": "physical_state",
    "value": "in_progress",
    "unit": null,
    "as_of": "2026-07-09",
    "source": "joy-2026-07-09-agenda-111",
    "locator": "article paragraph 14",
    "quote": "About three were commissioned, while they were not completed.",
    "stated_by": "Health Minister (statement to Parliament's Assurance Committee)",
    "tag": "FACT",
    "basis": "per_source",
    "source_term": "not completed",
    "note": "Programme-level state: about three hospitals commissioned unfinished, 35 identified for continuation. The Minister states that he visited the sites himself."
  },
  {
    "id": "agenda-111#3",
    "project": "agenda-111",
    "field": "amount_paid",
    "value": 4800000000,
    "unit": "GHS",
    "as_of": "2026-07-09",
    "source": "joy-2026-07-09-agenda-111",
    "locator": "article paragraph 1",
    "quote": "despite the previous administration spending about GH¢4.8 billion on the initiative",
    "stated_by": "Health Minister (statement to Parliament's Assurance Committee)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "Spent on the programme to date, as the Minister states it ('about'). Not an audited figure."
  },
  {
    "id": "agenda-111#4",
    "project": "agenda-111",
    "field": "amount_outstanding",
    "value": 1000000000,
    "unit": "GHS",
    "as_of": "2026-07-09",
    "source": "joy-2026-07-09-agenda-111",
    "locator": "article paragraph 2",
    "quote": "the government inherited more than GH¢1 billion in outstanding Interim Payment Certificates (IPCs) owed to contractors",
    "stated_by": "Health Minister (statement to Parliament's Assurance Committee)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "Unpaid contractor certificates. The Minister later says 'a little above GH¢1 billion'; the register holds the floor."
  },
  {
    "id": "agenda-111#5",
    "project": "agenda-111",
    "field": "cost_to_complete",
    "value": 20000000000,
    "unit": "GHS",
    "as_of": "2026-07-09",
    "source": "citi-2026-07-09-agenda-111-cost-to-complete",
    "locator": "article paragraph 4",
    "quote": "We need a little above 20 billion Ghana cedis.",
    "stated_by": "Health Minister (statement to Parliament's Assurance Committee)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "The Minister's estimate for all remaining Agenda 111 projects ('a little above'); no costed schedule is published."
  },
  {
    "id": "agenda-111#6",
    "project": "agenda-111",
    "field": "announcement",
    "value": "35 Agenda 111 projects identified for continuation; contractors directed to return to site; no completion dates given because some contracts may be terminated and repackaged.",
    "unit": null,
    "as_of": "2026-07-09",
    "source": "joy-2026-07-09-agenda-111",
    "locator": "article paragraph 3",
    "quote": "the government has identified 35 Agenda 111 projects for continuation, with contractors directed to return to their respective sites.",
    "stated_by": "Health Minister (statement to Parliament's Assurance Committee)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "agenda-111#7",
    "project": "agenda-111",
    "field": "announcement",
    "value": "The 2026 Budget provides for work to start on 10 of the 35 identified projects.",
    "unit": null,
    "as_of": "2026-07-09",
    "source": "joy-2026-07-09-agenda-111",
    "locator": "article paragraph 7",
    "quote": "if you check the 2026 Budget, we said we were going to start 10 in 2026.",
    "stated_by": "Health Minister (statement to Parliament's Assurance Committee)",
    "tag": "FUNDED",
    "basis": null,
    "source_term": null,
    "note": "The Minister refers to a budget provision; the amount for the 10 projects is not given in the source and is not recorded here."
  },
  {
    "id": "agenda-111#8",
    "project": "agenda-111",
    "field": "announcement",
    "value": "Church or CHAG partners may complete, equip and operate Agenda 111 facilities under agreements with the Ministry.",
    "unit": null,
    "as_of": "2026-07-09",
    "source": "citi-2026-07-09-agenda-111-cost-to-complete",
    "locator": "article paragraph 8",
    "quote": "if any church is interested in any of the Agenda 111 facilities, we will enter into an agreement with the church or CHAG and they will finish, equip and then operationalise it",
    "stated_by": "Health Minister (statement to Parliament's Assurance Committee)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "agenda-111#9",
    "project": "agenda-111",
    "field": "allegation",
    "value": "Some Agenda 111 hospitals were commissioned with temporary arrangements: generators were brought for the ceremony and removed afterwards, and the premises were locked.",
    "unit": null,
    "as_of": "2026-07-09",
    "source": "joy-2026-07-09-agenda-111",
    "locator": "article paragraph 16",
    "quote": "in some cases, generators were carried to the site for the commissioning, and after the commissioning, it was taken back, and the place was locked.",
    "stated_by": "Health Minister (statement to Parliament's Assurance Committee)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Allegation about the previous administration's commissioning ceremonies; the three commissioned sites are not named in this source."
  },
  {
    "id": "kpone-affordable-housing#1",
    "project": "kpone-affordable-housing",
    "field": "start_date",
    "value": "2006",
    "unit": null,
    "as_of": "2024-11-26",
    "source": "graphic-2024-11-26-kpone-phase-4",
    "locator": "article paragraph 4",
    "quote": "started in 2006",
    "stated_by": "Vice-President (speech at the inauguration and sod-cutting)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Project history as the Vice-President states it; no primary record held."
  },
  {
    "id": "kpone-affordable-housing#2",
    "project": "kpone-affordable-housing",
    "field": "allegation",
    "value": "The project was abandoned between 2009 and 2016 and was revived by the new board and management of the Tema Development Corporation.",
    "unit": null,
    "as_of": "2024-11-26",
    "source": "graphic-2024-11-26-kpone-phase-4",
    "locator": "article paragraph 4",
    "quote": "was abandoned between 2009 and 2016",
    "stated_by": "Vice-President (speech at the inauguration and sod-cutting)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "kpone-affordable-housing#3",
    "project": "kpone-affordable-housing",
    "field": "commissioning_date",
    "value": "2024-11",
    "unit": null,
    "as_of": "2024-11-26",
    "source": "graphic-2024-11-26-kpone-phase-4",
    "locator": "article paragraph 3",
    "quote": "inaugurated a 1,072 housing units part of the Kpone (Community 26) affordable housing facility",
    "stated_by": "Graphic Online (reporter)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "Date is the report's publication date (26 November 2024); the day of the inauguration is not stated."
  },
  {
    "id": "kpone-affordable-housing#4",
    "project": "kpone-affordable-housing",
    "field": "capacity",
    "value": 1072,
    "unit": "units",
    "as_of": "2024-11-26",
    "source": "graphic-2024-11-26-kpone-phase-4",
    "locator": "article paragraph 3",
    "quote": "inaugurated a 1,072 housing units part of the Kpone (Community 26) affordable housing facility",
    "stated_by": "Graphic Online (reporter)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "Units inaugurated (phases one to three). Occupancy is not stated."
  },
  {
    "id": "kpone-affordable-housing#5",
    "project": "kpone-affordable-housing",
    "field": "capacity",
    "value": 832,
    "unit": "units",
    "as_of": "2024-11-26",
    "source": "graphic-2024-11-26-kpone-phase-4",
    "locator": "article paragraph 1",
    "quote": "cut the sod for the construction of 832 additional housing units at Kpone",
    "stated_by": "Vice-President (speech at the inauguration and sod-cutting)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Phase four, as announced in 2024. The Minister's 2026 figure is 800 units."
  },
  {
    "id": "kpone-affordable-housing#6",
    "project": "kpone-affordable-housing",
    "field": "operational_state",
    "value": "partly_operating",
    "unit": null,
    "as_of": "2026-04-15",
    "source": "graphic-2026-04-16-kpone-phase-4",
    "locator": "article paragraph 8",
    "quote": "Already, Phases One to Three of the project have delivered 1,000 housing units.",
    "stated_by": "Minister for Works, Housing and Water Resources",
    "tag": "FACT",
    "basis": "per_source",
    "source_term": "delivered",
    "note": "Phases one to three delivered; phase four under construction. Occupancy is not stated."
  },
  {
    "id": "kpone-affordable-housing#7",
    "project": "kpone-affordable-housing",
    "field": "physical_state",
    "value": "in_progress",
    "unit": null,
    "as_of": "2026-04-15",
    "source": "graphic-2026-04-16-kpone-phase-4",
    "locator": "article paragraph 5",
    "quote": "Construction, which began in 2025, has reached advanced stages, with several buildings currently at roofing, plastering and painting levels.",
    "stated_by": "Graphic Online (reporter, on the Minister's inspection)",
    "tag": "FACT",
    "basis": "per_source",
    "source_term": "advanced stages",
    "note": null
  },
  {
    "id": "kpone-affordable-housing#8",
    "project": "kpone-affordable-housing",
    "field": "capacity",
    "value": 800,
    "unit": "units",
    "as_of": "2026-04-15",
    "source": "graphic-2026-04-16-kpone-phase-4",
    "locator": "article paragraph 4",
    "quote": "the significant progress made on the 800 two-bedroom housing units under Phase Four of the Kpone Affordable Housing Project",
    "stated_by": "Minister for Works, Housing and Water Resources",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Phase four, two-bedroom units."
  },
  {
    "id": "kpone-affordable-housing#9",
    "project": "kpone-affordable-housing",
    "field": "completion_date_planned",
    "value": "2026-09",
    "unit": null,
    "as_of": "2026-04-15",
    "source": "graphic-2026-04-16-kpone-phase-4",
    "locator": "article paragraph 4",
    "quote": "which is expected to be completed by September this year",
    "stated_by": "Minister for Works, Housing and Water Resources",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Phase four. The Housing Minister's January 2026 'June 2027' completion date refers to the Oxygen City project in the Volta Region, not to Kpone."
  },
  {
    "id": "kpone-affordable-housing#10",
    "project": "kpone-affordable-housing",
    "field": "physical_progress",
    "value": 90,
    "unit": "percent",
    "as_of": "2026-04-15",
    "source": "isd-2026-04-16-kpone-inspection",
    "locator": "article paragraph 2",
    "quote": "Work on both phases, which commenced in 2025, is now 90% complete.",
    "stated_by": "Information Services Department, reporting the Minister's inspection",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "Phases IV and V together, over 1,000 two-bedroom units."
  },
  {
    "id": "kpone-affordable-housing#11",
    "project": "kpone-affordable-housing",
    "field": "announcement",
    "value": "Contracts under the project could be terminated over poor performance; one contractor responsible for 10 blocks is significantly behind schedule.",
    "unit": null,
    "as_of": "2026-04-15",
    "source": "graphic-2026-04-16-kpone-phase-4",
    "locator": "article paragraph 17",
    "quote": "warned contractors under the Kpone Affordable Housing Project that contracts could be terminated over poor performance",
    "stated_by": "Managing Director, TDC Ghana Ltd",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "saglemi-housing#1",
    "project": "saglemi-housing",
    "field": "capacity",
    "value": 5000,
    "unit": "units",
    "as_of": "2012-08",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 8",
    "quote": "granted executive approval to the Ministry of Water Resources, Works and Housing (MWRWH) for the construction of 5000 affordable housing units (the Saglemi Affordable Housing Project)",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "saglemi-housing#2",
    "project": "saglemi-housing",
    "field": "loan_amount",
    "value": 200000000,
    "unit": "USD",
    "as_of": "2013-01-04",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 11",
    "quote": "On 4th January 2013, a Facility Agreement was signed between the Ministry of Finance, as the borrower, and Credit Suisse, as the creditor, for a facility of $200million for the construction of 5000 housing units.",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "A buyer's credit from Credit Suisse International. The filing says US$198,450,000 was disbursed into escrow on 9 January 2013."
  },
  {
    "id": "saglemi-housing#3",
    "project": "saglemi-housing",
    "field": "award_date",
    "value": "2013-01-04",
    "unit": null,
    "as_of": "2013-01-04",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 12",
    "quote": "signed an Engineering, Procurement and Construction (EPC) Agreement with Construtora OAS Ghana Ltd",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "EPC agreement signed on the same day as the facility agreement."
  },
  {
    "id": "saglemi-housing#4",
    "project": "saglemi-housing",
    "field": "contract_sum",
    "value": 200000000,
    "unit": "USD",
    "as_of": "2013-01-04",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 13",
    "quote": "at a contract price of US$ 200million, including consultancy services",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "saglemi-housing#5",
    "project": "saglemi-housing",
    "field": "capacity",
    "value": 1412,
    "unit": "units",
    "as_of": "2016-12-21",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 32",
    "quote": "further reduction in the scope of works to 1,412 housing units",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "Scope after the second restated agreement. The filing says an earlier restatement of 27 February 2014 reduced the scope to about 1,502 units in the first phase."
  },
  {
    "id": "saglemi-housing#6",
    "project": "saglemi-housing",
    "field": "revised_contract_sum",
    "value": 181018000,
    "unit": "USD",
    "as_of": "2016-12-21",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 32",
    "quote": "revised contract price of US$ l81,018,000.00 and extended the completion period of the contract to 31st July 2017",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "The source prints the figure as 'l81,018,000.00' (a typographical error for 181,018,000.00). The filing says the restatement was made without parliamentary approval."
  },
  {
    "id": "saglemi-housing#7",
    "project": "saglemi-housing",
    "field": "completion_date_planned",
    "value": "2017-07-31",
    "unit": null,
    "as_of": "2016-12-21",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 32",
    "quote": "extended the completion period of the contract to 31st July 2017 without any basis",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "saglemi-housing#8",
    "project": "saglemi-housing",
    "field": "amount_paid",
    "value": 179904757.78,
    "unit": "USD",
    "as_of": "2021-08",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 37",
    "quote": "with the contractor having been paid $179,904, 757.78",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Paid to the contractor, as the Attorney-General alleged in a court filing reported on 1 August 2021. Itemised in the filing: US$80m advance (27 February 2013), US$46.1m (March 2014 to January 2015), US$54.1m (June 2015 to January 2017). The charges were withdrawn on 7 February 2025 and no court tested the figure."
  },
  {
    "id": "saglemi-housing#9",
    "project": "saglemi-housing",
    "field": "amount_paid",
    "value": 196428891.66,
    "unit": "USD",
    "as_of": "2021-08",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 37",
    "quote": "Even though a total amount of $196,428,891.66 has been spent on the Saglemi Affordable Housing Project",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Total spent on the project, including consultants, as the Attorney-General alleged. Not additive with the contractor figure above, which it contains."
  },
  {
    "id": "saglemi-housing#10",
    "project": "saglemi-housing",
    "field": "allegation",
    "value": "The contractor was paid US$179.9m although the cost of works executed on site, including consultancy services, was about US$64.98m; only 668 housing units were completed, none habitable or sold, and the facility remains unpaid.",
    "unit": null,
    "as_of": "2021-08-01",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 37",
    "quote": "investigations revealed that the cost of works executed on the site, including consultancy services, is about $64,982,900.77.",
    "stated_by": "Attorney-General (court filing)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Disputed. The accused faced charges; the Attorney-General withdrew all of them in February 2025 (decision below)."
  },
  {
    "id": "saglemi-housing#11",
    "project": "saglemi-housing",
    "field": "capacity",
    "value": 668,
    "unit": "units",
    "as_of": "2021-08-01",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 38",
    "quote": "Investigations further revealed that only 668 housing units were completed by the contractor.",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Units the Attorney-General says the contractor completed."
  },
  {
    "id": "saglemi-housing#12",
    "project": "saglemi-housing",
    "field": "operational_state",
    "value": "not_operating",
    "unit": null,
    "as_of": "2021-08-01",
    "source": "joy-2021-08-01-saglemi-ag-filing",
    "locator": "article paragraph 39",
    "quote": "These houses are, however, not habitable and none under the project has been sold and the Facility remains unpaid",
    "stated_by": "Attorney-General (court filing, as reported by MyJoyOnline)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "not habitable",
    "note": null
  },
  {
    "id": "saglemi-housing#13",
    "project": "saglemi-housing",
    "field": "decision",
    "value": "The Attorney-General withdrew all charges in the Saglemi case against the five accused by a nolle prosequi notice filed at the High Court (Financial Division 1) on 7 February 2025.",
    "unit": null,
    "as_of": "2025-02-07",
    "source": "citi-2025-02-08-saglemi-charges-dropped",
    "locator": "article paragraph 3",
    "quote": "The notice, signed by the Attorney-General, officially marks the end of the state's case against the accused individuals.",
    "stated_by": "Attorney-General (nolle prosequi notice)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "The report says one accused, the contractor's executive chairman, is deceased. It gives 70 charges; the 2021 report gave 52."
  },
  {
    "id": "saglemi-housing#14",
    "project": "saglemi-housing",
    "field": "physical_state",
    "value": "stalled",
    "unit": null,
    "as_of": "2025",
    "source": "joy-2026-08-20-saglemi-700-units",
    "locator": "article paragraph 5",
    "quote": "before it stalled following a change of government and subsequent legal and investigative issues",
    "stated_by": "President (Presidency statement and site tour, 20 August 2026)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "stalled",
    "note": "The President describes the period from the change of government to the selection of a developer; the year is approximate. The Ghanaian Times report of 24 August 2026 quotes him on 'almost a decade of neglect'."
  },
  {
    "id": "saglemi-housing#15",
    "project": "saglemi-housing",
    "field": "allegation",
    "value": "The stalled site was vandalised: cables, wash basins, baths, fittings and bulbs were stolen, and underground telecommunications cables removed.",
    "unit": null,
    "as_of": "2026-08-20",
    "source": "joy-2026-08-20-saglemi-700-units",
    "locator": "article paragraph 8",
    "quote": "Looters came in and stole everything, the cables, the wash basins, the baths, all the fittings, electrical bulbs",
    "stated_by": "President (Presidency statement and site tour, 20 August 2026)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "saglemi-housing#16",
    "project": "saglemi-housing",
    "field": "physical_state",
    "value": "in_progress",
    "unit": null,
    "as_of": "2026-08-20",
    "source": "joy-2026-08-20-saglemi-700-units",
    "locator": "article paragraph 3",
    "quote": "where construction work is ongoing to complete the residential community",
    "stated_by": "MyJoyOnline (reporter, on the President's tour)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "construction work is ongoing",
    "note": null
  },
  {
    "id": "saglemi-housing#17",
    "project": "saglemi-housing",
    "field": "operational_state",
    "value": "not_operating",
    "unit": null,
    "as_of": "2026-08-20",
    "source": "joy-2026-08-20-saglemi-700-units",
    "locator": "article paragraph 4",
    "quote": "prospective homeowners to prepare to register for the houses once the official registration portal is opened.",
    "stated_by": "MyJoyOnline (reporter)",
    "tag": "ANNOUNCED",
    "basis": "derived",
    "source_term": null,
    "note": "No unit is reported occupied; sales had not opened."
  },
  {
    "id": "saglemi-housing#18",
    "project": "saglemi-housing",
    "field": "completion_date_planned",
    "value": "2027-03",
    "unit": null,
    "as_of": "2026-08-20",
    "source": "joy-2026-08-20-saglemi-700-units",
    "locator": "article paragraph 1",
    "quote": "the first 700 housing units at the Saglemi Affordable Housing Project are expected to be completed and commissioned by March 2027",
    "stated_by": "President (Presidency statement and site tour, 20 August 2026)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "First 700 units, built by the selected developer LMI Holdings."
  },
  {
    "id": "saglemi-housing#19",
    "project": "saglemi-housing",
    "field": "completion_date_planned",
    "value": "2027-12",
    "unit": null,
    "as_of": "2026-08-20",
    "source": "joy-2026-08-20-saglemi-700-units",
    "locator": "article paragraph 2",
    "quote": "1,500 housing units to be completed by the end of 2027",
    "stated_by": "President (Presidency statement and site tour, 20 August 2026)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "First phase of 1,500 units."
  },
  {
    "id": "saglemi-housing#20",
    "project": "saglemi-housing",
    "field": "announcement",
    "value": "Work is to begin immediately on a further 3,500 units, to bring the estate to the 5,000 units originally planned.",
    "unit": null,
    "as_of": "2026-08-24",
    "source": "gt-2026-08-24-saglemi-first-700",
    "locator": "article paragraph 3",
    "quote": "while work would begin immediately on the additional 3,500 units to bring the estate to the 5,000 units originally envisaged",
    "stated_by": "President (working tour of Saglemi)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "tema-mpakadan-railway#1",
    "project": "tema-mpakadan-railway",
    "field": "commissioning_date",
    "value": "2024-11-22",
    "unit": null,
    "as_of": "2025-05-20",
    "source": "graphic-2025-05-20-tema-mpakadan-inactive",
    "locator": "article paragraph 1",
    "quote": "Six months after the official opening of the 97.7-kilometre Tema-Mpakadan railway operations on Friday, November 22, 2024, the much-publicised service remains inactive",
    "stated_by": "Graphic Online (reporter)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "Inaugurated by the then President with two Diesel Multiple Unit trains."
  },
  {
    "id": "tema-mpakadan-railway#2",
    "project": "tema-mpakadan-railway",
    "field": "capacity",
    "value": 97.7,
    "unit": "km",
    "as_of": "2025-05-20",
    "source": "graphic-2025-05-20-tema-mpakadan-inactive",
    "locator": "article paragraph 1",
    "quote": "Six months after the official opening of the 97.7-kilometre Tema-Mpakadan railway operations on Friday, November 22, 2024, the much-publicised service remains inactive",
    "stated_by": "Graphic Online (reporter)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "tema-mpakadan-railway#3",
    "project": "tema-mpakadan-railway",
    "field": "total_cost",
    "value": 447000000,
    "unit": "USD",
    "as_of": "2025-05-20",
    "source": "graphic-2025-05-20-tema-mpakadan-inactive",
    "locator": "article paragraph 3",
    "quote": "Constructed at a cost of US$447 million through a credit facility from the India Export-Import Bank",
    "stated_by": "Graphic Online (reporter, no document cited)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "The source gives a construction cost, not the loan amount; no primary document is cited."
  },
  {
    "id": "tema-mpakadan-railway#4",
    "project": "tema-mpakadan-railway",
    "field": "physical_state",
    "value": "completed",
    "unit": null,
    "as_of": "2025-05-20",
    "source": "graphic-2025-05-20-tema-mpakadan-inactive",
    "locator": "article paragraph 3",
    "quote": "Constructed at a cost of US$447 million through a credit facility from the India Export-Import Bank",
    "stated_by": "Graphic Online (reporter)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "Constructed",
    "note": "The July 2026 report below says several systems were incomplete or not functional when the line was commissioned."
  },
  {
    "id": "tema-mpakadan-railway#5",
    "project": "tema-mpakadan-railway",
    "field": "operational_state",
    "value": "not_operating",
    "unit": null,
    "as_of": "2025-05-20",
    "source": "graphic-2025-05-20-tema-mpakadan-inactive",
    "locator": "article paragraph 1",
    "quote": "Six months after the official opening of the 97.7-kilometre Tema-Mpakadan railway operations on Friday, November 22, 2024, the much-publicised service remains inactive",
    "stated_by": "Graphic Online (reporter)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "remains inactive",
    "note": null
  },
  {
    "id": "tema-mpakadan-railway#6",
    "project": "tema-mpakadan-railway",
    "field": "announcement",
    "value": "About 75 per cent of the vandalism and theft damage has been repaired; commercial operations were held back by theft and vandalism and by the absence of private operators.",
    "unit": null,
    "as_of": "2025-05-20",
    "source": "graphic-2025-05-20-tema-mpakadan-inactive",
    "locator": "article paragraph 8",
    "quote": "about 75 per cent of the damage has so far been repaired",
    "stated_by": "Acting Chief Executive Officer, Ghana Railway Development Authority",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "tema-mpakadan-railway#7",
    "project": "tema-mpakadan-railway",
    "field": "announcement",
    "value": "Full commercial operations could begin by 20 June 2026.",
    "unit": null,
    "as_of": "2025-05-20",
    "source": "graphic-2025-05-20-tema-mpakadan-inactive",
    "locator": "article paragraph 13",
    "quote": "full commercial operations could begin by June 20, 2026.",
    "stated_by": "Acting Chief Executive Officer, Ghana Railway Development Authority",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "No source found that confirms full commercial operations on or after 20 June 2026. The 6 July 2026 report below says works were still outstanding."
  },
  {
    "id": "tema-mpakadan-railway#8",
    "project": "tema-mpakadan-railway",
    "field": "operational_state",
    "value": "partly_operating",
    "unit": null,
    "as_of": "2025-10-01",
    "source": "graphic-2025-10-01-tema-mpakadan-reactivated",
    "locator": "article paragraph 1",
    "quote": "The Ghana Railways Development Authority (GRDA) on Wednesday, October 1, 2025, reactivated commercial operations on the Tema-Mpakadan railway line.",
    "stated_by": "Graphic Online (reporter)",
    "tag": "FACT",
    "basis": "per_source",
    "source_term": "reactivated commercial operations",
    "note": "The reported first trip ran from Tema Harbour to Afienya; fares were set for Tema-Afienya (GH¢15) and Afienya-Adorme (GH¢25)."
  },
  {
    "id": "tema-mpakadan-railway#9",
    "project": "tema-mpakadan-railway",
    "field": "physical_state",
    "value": "in_progress",
    "unit": null,
    "as_of": "2026-07-06",
    "source": "citi-2026-07-06-tema-mpakadan-eu-grant",
    "locator": "article paragraph 2",
    "quote": "a forensic audit conducted under the current administration revealed that several essential systems on the line were either incomplete or not functional at the time of its commissioning",
    "stated_by": "Ghana Railway Development Authority (press briefing, as reported by Citi Newsroom)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "incomplete or not functional",
    "note": "Signalling, public address, level crossing controls and point machines. The forensic audit is not published."
  },
  {
    "id": "tema-mpakadan-railway#10",
    "project": "tema-mpakadan-railway",
    "field": "operational_state",
    "value": "unknown",
    "unit": null,
    "as_of": "2026-07-06",
    "source": "citi-2026-07-06-tema-mpakadan-eu-grant",
    "locator": "article paragraph 1",
    "quote": "following concerns about its readiness for full commercial operation",
    "stated_by": "Citi Newsroom (reporter)",
    "tag": "ANNOUNCED",
    "basis": "derived",
    "source_term": null,
    "note": "The source does not say whether services were running. It frames the line as not yet ready for full commercial operation."
  },
  {
    "id": "tema-mpakadan-railway#11",
    "project": "tema-mpakadan-railway",
    "field": "grant_amount",
    "value": 21000000,
    "unit": "USD",
    "as_of": "2026-07-06",
    "source": "citi-2026-07-06-tema-mpakadan-eu-grant",
    "locator": "article paragraph 8",
    "quote": "we have been awarded 21 million US dollars by the EU Commission as a grant to fix the signalling system with ETCS Level 1",
    "stated_by": "Chief Executive Officer, Ghana Railway Development Authority",
    "tag": "FUNDED",
    "basis": null,
    "source_term": null,
    "note": "A European Union grant to complete and upgrade the signalling system with ETCS Level 1."
  },
  {
    "id": "weija-childrens-hospital#1",
    "project": "weija-childrens-hospital",
    "field": "capacity",
    "value": 120,
    "unit": "beds",
    "as_of": "2026-05-25",
    "source": "joy-2026-05-25-weija-world-bank",
    "locator": "article paragraph 2",
    "quote": "the 120-bed specialised paediatric hospital at Weija was built and equipped under the World Bank-funded COVID-19 Emergency Preparedness and Response Project at a total cost of US$10.15 million",
    "stated_by": "World Bank (statement of 25 May 2026)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "Bed count differs across sources: 120 (World Bank, Ministry, MyJoyOnline) and 130 (EOCO, 11 August 2026)."
  },
  {
    "id": "weija-childrens-hospital#2",
    "project": "weija-childrens-hospital",
    "field": "total_cost",
    "value": 10150000,
    "unit": "USD",
    "as_of": "2026-05-25",
    "source": "joy-2026-05-25-weija-world-bank",
    "locator": "article paragraph 2",
    "quote": "the 120-bed specialised paediatric hospital at Weija was built and equipped under the World Bank-funded COVID-19 Emergency Preparedness and Response Project at a total cost of US$10.15 million",
    "stated_by": "World Bank (statement of 25 May 2026)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "The World Bank's 'total cost' of the built and equipped facility; the contract itself is not published. The December 2025 report values the hospital at US$14 million."
  },
  {
    "id": "weija-childrens-hospital#3",
    "project": "weija-childrens-hospital",
    "field": "announcement",
    "value": "The World Bank project (P173788) closed on 16 December 2025 after a six-month extension.",
    "unit": null,
    "as_of": "2025-12-16",
    "source": "joy-2026-05-25-weija-world-bank",
    "locator": "article paragraph 4",
    "quote": "the project officially closed on December 16, 2025, after a six-month extension",
    "stated_by": "World Bank (statement of 25 May 2026)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "weija-childrens-hospital#4",
    "project": "weija-childrens-hospital",
    "field": "physical_state",
    "value": "in_progress",
    "unit": null,
    "as_of": "2025-12-16",
    "source": "joy-2026-05-25-weija-world-bank",
    "locator": "article paragraph 7",
    "quote": "several components of the project remained unfinished, including the installation of some medical equipment",
    "stated_by": "World Bank (statement of 25 May 2026)",
    "tag": "FACT",
    "basis": "per_source",
    "source_term": "remained unfinished",
    "note": "State at project closure as the Bank describes it: built, with some equipment installation and environmental and social safeguard measures outstanding."
  },
  {
    "id": "weija-childrens-hospital#5",
    "project": "weija-childrens-hospital",
    "field": "operational_state",
    "value": "not_operating",
    "unit": null,
    "as_of": "2026-05-25",
    "source": "joy-2026-05-25-weija-world-bank",
    "locator": "article paragraph 12",
    "quote": "To fully operationalise the hospital, the Government will need to complete these necessary actions and assign staff to the facility",
    "stated_by": "World Bank (statement of 25 May 2026)",
    "tag": "FACT",
    "basis": "derived",
    "source_term": null,
    "note": "The Bank urges the Government to open the hospital, which implies it is not yet operating."
  },
  {
    "id": "weija-childrens-hospital#6",
    "project": "weija-childrens-hospital",
    "field": "physical_state",
    "value": "stalled",
    "unit": null,
    "as_of": "2025-12-12",
    "source": "joy-2025-12-12-weija-halt",
    "locator": "article paragraph 1",
    "quote": "has stalled due to an alleged unilateral abrogation of the contract for its construction by the funding agency",
    "stated_by": "MyJoyOnline (reporter, relaying activists and residents)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "stalled",
    "note": "Contested: the contractor said in a press release dated 12 December 2025 that it had given no interview and that the project was practically complete (below); the Ministry said in May 2026 that the Bank declined to settle payments, not that it cancelled the contract."
  },
  {
    "id": "weija-childrens-hospital#7",
    "project": "weija-childrens-hospital",
    "field": "physical_progress",
    "value": 65,
    "unit": "percent",
    "as_of": "2025-12-12",
    "source": "joy-2025-12-12-weija-halt",
    "locator": "article paragraph 5",
    "quote": "The new 120-bed facility valued at $14 million is already 65% complete, according to the contractor on the site",
    "stated_by": "MyJoyOnline, attributing the figure to the contractor on site (Awerco Construction Limited)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Disputed by the same contractor in a press release dated 12 December 2025 (below)."
  },
  {
    "id": "weija-childrens-hospital#8",
    "project": "weija-childrens-hospital",
    "field": "total_cost",
    "value": 14000000,
    "unit": "USD",
    "as_of": "2025-12-12",
    "source": "joy-2025-12-12-weija-halt",
    "locator": "article paragraph 5",
    "quote": "The new 120-bed facility valued at $14 million is already 65% complete, according to the contractor on the site",
    "stated_by": "MyJoyOnline (reporter, no document cited)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "A valuation given by the reporter. The article also says 'some $14 million has already been invested'. The World Bank later states a total cost of US$10.15 million."
  },
  {
    "id": "weija-childrens-hospital#9",
    "project": "weija-childrens-hospital",
    "field": "allegation",
    "value": "The World Bank cancelled the construction contract, stopping work; the cancellation is said to rest on price inconsistencies, no Public Procurement Authority approval and no value-for-money audit.",
    "unit": null,
    "as_of": "2025-12-12",
    "source": "joy-2025-12-12-weija-halt",
    "locator": "article paragraph 3",
    "quote": "The cancellation of the project is said to be due to price inconsistencies, lack of approval from the Public Procurement Authority (PPA), and the lack of a value for money audit, among others.",
    "stated_by": "MyJoyOnline (reporter, relaying concerned residents and activists)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "The article itself says these reasons 'have not been proven to be true'. No source held here has the contractor, the World Bank or the Ministry confirming a cancellation."
  },
  {
    "id": "weija-childrens-hospital#10",
    "project": "weija-childrens-hospital",
    "field": "announcement",
    "value": "No notice of termination or cancellation has been received; the contract is with the Ministry of Health, not the World Bank; the only outstanding issue is payments due from the Ministry; the contractor gave no interview to any media house.",
    "unit": null,
    "as_of": "2025-12-12",
    "source": "joy-2025-12-13-weija-awerco-denial",
    "locator": "article paragraph 5",
    "quote": "there has been no notice whatsoever of contract termination or cancellation",
    "stated_by": "Awerco Construction Limited (press release dated 12 December 2025, signed by its Managing Director)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "weija-childrens-hospital#11",
    "project": "weija-childrens-hospital",
    "field": "physical_state",
    "value": "in_progress",
    "unit": null,
    "as_of": "2025-12-12",
    "source": "joy-2025-12-13-weija-awerco-denial",
    "locator": "article paragraph 3",
    "quote": "the Weija Paediatric Hospital Project is practically completed in line with the contract scope and is currently undergoing snagging works in collaboration with the Ministry of Health.",
    "stated_by": "Awerco Construction Limited (press release dated 12 December 2025)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "practically completed ... undergoing snagging works",
    "note": "The contractor's own description. It also states that all medical equipment required under the contract had been supplied and installed; the Ministry and the World Bank say some equipment was not installed."
  },
  {
    "id": "weija-childrens-hospital#12",
    "project": "weija-childrens-hospital",
    "field": "start_date",
    "value": "2023",
    "unit": null,
    "as_of": "2026-05-06",
    "source": "adom-2026-05-06-weija-ministry-statement",
    "locator": "article paragraph 3",
    "quote": "The hospital is a World Bank-funded project, which commenced in 2023 and was expected to be completed in December 2025",
    "stated_by": "Ministry of Health spokesperson",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": "Construction start as the Ministry states it."
  },
  {
    "id": "weija-childrens-hospital#13",
    "project": "weija-childrens-hospital",
    "field": "completion_date_planned",
    "value": "2025-12",
    "unit": null,
    "as_of": "2026-05-06",
    "source": "adom-2026-05-06-weija-ministry-statement",
    "locator": "article paragraph 3",
    "quote": "The hospital is a World Bank-funded project, which commenced in 2023 and was expected to be completed in December 2025",
    "stated_by": "Ministry of Health spokesperson",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "weija-childrens-hospital#14",
    "project": "weija-childrens-hospital",
    "field": "allegation",
    "value": "In 2024 the World Bank raised concerns about misprocurement, including medical equipment priced up to about 11 times the actual price, and declined to settle all outstanding payments.",
    "unit": null,
    "as_of": "2026-05-06",
    "source": "adom-2026-05-06-weija-ministry-statement",
    "locator": "article paragraph 5",
    "quote": "in 2024, the World Bank raised concerns about misprocurement, which included inflated costs of medical equipment—up to about 11 times the actual price.",
    "stated_by": "Ministry of Health spokesperson",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "A Ministry statement issued after the residents' demonstration of 5 May 2026. No World Bank finding is cited."
  },
  {
    "id": "weija-childrens-hospital#15",
    "project": "weija-childrens-hospital",
    "field": "allegation",
    "value": "The contractor halted the Ministry's preparations to commission the hospital, insisting that all outstanding issues be resolved before it granted access.",
    "unit": null,
    "as_of": "2026-05-06",
    "source": "adom-2026-05-06-weija-ministry-statement",
    "locator": "article paragraph 9",
    "quote": "the contractor subsequently halted this process, insisting that all outstanding issues be fully resolved before granting access to the hospital.",
    "stated_by": "Ministry of Health spokesperson",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "weija-childrens-hospital#16",
    "project": "weija-childrens-hospital",
    "field": "operational_state",
    "value": "not_operating",
    "unit": null,
    "as_of": "2026-05-06",
    "source": "adom-2026-05-06-weija-ministry-statement",
    "locator": "article paragraph 8",
    "quote": "Despite efforts to make the facility operational, the process was halted.",
    "stated_by": "Ministry of Health spokesperson",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "the process was halted",
    "note": null
  },
  {
    "id": "weija-childrens-hospital#17",
    "project": "weija-childrens-hospital",
    "field": "physical_state",
    "value": "in_progress",
    "unit": null,
    "as_of": "2026-07-08",
    "source": "joy-2026-07-08-weija-ready-to-open",
    "locator": "article paragraph 1",
    "quote": "the contractor’s inability to complete outstanding works and officially hand over the facility to the Ministry",
    "stated_by": "Health Minister (statement to Parliament, 8 July 2026)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "outstanding works",
    "note": "Conflicts with the contractor's December 2025 'practically completed' and with EOCO's 16 July 2026 'completed facility'. The Minister says Ghana Health Service assessments confirm parts of the project remain incomplete."
  },
  {
    "id": "weija-childrens-hospital#18",
    "project": "weija-childrens-hospital",
    "field": "operational_state",
    "value": "not_operating",
    "unit": null,
    "as_of": "2026-07-08",
    "source": "joy-2026-07-08-weija-ready-to-open",
    "locator": "article paragraph 3",
    "quote": "the hospital cannot begin operations because some critical components, including the installation of medical equipment, are yet to be completed",
    "stated_by": "Health Minister (statement to Parliament, 8 July 2026)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "cannot begin operations",
    "note": null
  },
  {
    "id": "weija-childrens-hospital#19",
    "project": "weija-childrens-hospital",
    "field": "allegation",
    "value": "In the course of construction the World Bank raised issues of misprocurement.",
    "unit": null,
    "as_of": "2026-07-08",
    "source": "joy-2026-07-08-weija-ready-to-open",
    "locator": "article paragraph 5",
    "quote": "the World Bank raised issues of what we call misprocurement",
    "stated_by": "Health Minister (statement to Parliament, 8 July 2026)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "weija-childrens-hospital#20",
    "project": "weija-childrens-hospital",
    "field": "announcement",
    "value": "The Ministry will commission the hospital within 24 hours of handover, with the full complement of staff on standby.",
    "unit": null,
    "as_of": "2026-07-08",
    "source": "joy-2026-07-08-weija-ready-to-open",
    "locator": "article paragraph 11",
    "quote": "if the project is handed over this morning, within the next 24 hours, we don't even need any fanfare. We will commission the project because we have the full complement of staff for that particular facility",
    "stated_by": "Health Minister (statement to Parliament, 8 July 2026)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "weija-childrens-hospital#21",
    "project": "weija-childrens-hospital",
    "field": "physical_state",
    "value": "completed",
    "unit": null,
    "as_of": "2026-07-16",
    "source": "citi-2026-07-16-weija-eoco-deal",
    "locator": "article paragraph 3",
    "quote": "The parties agreed that the completed facility should be handed over and made operational without further delay, in the interest of the public.",
    "stated_by": "Economic and Organised Crime Office (statement dated 16 July 2026, as reported by Citi Newsroom)",
    "tag": "ANNOUNCED",
    "basis": "per_source",
    "source_term": "completed facility",
    "note": "Conflicts with the Minister's statement of 8 July 2026 that works were outstanding."
  },
  {
    "id": "weija-childrens-hospital#22",
    "project": "weija-childrens-hospital",
    "field": "announcement",
    "value": "The contractor handed the hospital over to the Ministry of Health on 7 August 2026, monitored by EOCO. EOCO's investigations into alleged procurement breaches and financial impropriety on the project remain ongoing.",
    "unit": null,
    "as_of": "2026-08-07",
    "source": "joy-2026-08-11-weija-handed-over",
    "locator": "article paragraph 2",
    "quote": "The handover ceremony, monitored by the Economic and Organised Crime Office (EOCO), took place on August 7, 2026, at the Conference Room of the Weija Paediatric Hospital.",
    "stated_by": "Economic and Organised Crime Office (statement of 11 August 2026, as reported by MyJoyOnline)",
    "tag": "FACT",
    "basis": null,
    "source_term": null,
    "note": null
  },
  {
    "id": "weija-childrens-hospital#23",
    "project": "weija-childrens-hospital",
    "field": "capacity",
    "value": 130,
    "unit": "beds",
    "as_of": "2026-08-11",
    "source": "joy-2026-08-11-weija-handed-over",
    "locator": "article paragraph 1",
    "quote": "has handed over the 130-bed facility to the Ministry of Health",
    "stated_by": "Economic and Organised Crime Office (as reported by MyJoyOnline)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": "Conflicts with the 120 beds stated by the World Bank and the Ministry."
  },
  {
    "id": "weija-childrens-hospital#24",
    "project": "weija-childrens-hospital",
    "field": "operational_state",
    "value": "partly_operating",
    "unit": null,
    "as_of": "2026-10-03",
    "source": "joy-2026-10-03-weija-operational",
    "locator": "article paragraph 1",
    "quote": "The Weija Children’s Specialist Hospital is now operational, with the 120-bed facility providing outpatient and emergency services",
    "stated_by": "Health Minister (announcement after an inspection)",
    "tag": "FACT",
    "basis": "per_source",
    "source_term": "now operational",
    "note": "Outpatient and emergency services only; inpatient services are being introduced. This is the Minister's account; the register holds no site observation."
  },
  {
    "id": "weija-childrens-hospital#25",
    "project": "weija-childrens-hospital",
    "field": "physical_state",
    "value": "in_progress",
    "unit": null,
    "as_of": "2026-10-03",
    "source": "joy-2026-10-03-weija-operational",
    "locator": "article paragraph 6",
    "quote": "almost all the equipment required for the facility had been installed",
    "stated_by": "Health Minister (announcement after an inspection)",
    "tag": "FACT",
    "basis": "per_source",
    "source_term": "almost all the equipment required for the facility had been installed",
    "note": null
  },
  {
    "id": "weija-childrens-hospital#26",
    "project": "weija-childrens-hospital",
    "field": "announcement",
    "value": "Ten additional doctors and 30 nurses and midwives are to be deployed to the hospital with immediate effect.",
    "unit": null,
    "as_of": "2026-10-03",
    "source": "joy-2026-10-03-weija-operational",
    "locator": "article paragraph 8",
    "quote": "I have directed that with immediate effect, they should bring an additional 10 medical doctors and 30 nurses and midwives to beef up the health workforce.",
    "stated_by": "Health Minister (announcement after an inspection)",
    "tag": "ANNOUNCED",
    "basis": null,
    "source_term": null,
    "note": null
  }
]